TSMC

Arizona Fab 21 Phase 1

Phoenix, AZ, USA

Operational
StatusConfirmedScheduleConfirmedInvestmentUnverifiedWhat do these mean?
LinkedInX

Investment

Undisclosed

CHIPS Act Funding

$6.6B

Technology Node

N4

Jobs Created

6,000

Project Type

Logic Fab

Planned HVM Start

Jan 1, 2024

Actual HVM Start

Oct 1, 2024

Last Updated

Sep 19, 2026

Schedule slippage

On schedule

Measured from the end of 2024, so this is a minimum.

See where the first target came from

The official source and date behind this baseline.

Upgrade to Pro

Timeline

No milestones recorded for this project yet.

History of Changes

Data correction: TSMC describes its Arizona investment as one cumulative program (total $265 billion), not per-phase amounts. Phase-level figures were removed to avoid double-counting; the program total is shown on the Phase 3 onward entry.

Sep 19, 2026 · investment_usd changed from "65000000000" to "null"

1 earlier change in the full history

Every change to this project, each with its source.

Upgrade to Pro

CHIPS Act Funding

$6.6B

Direct funding award disclosed by the U.S. Department of Commerce's CHIPS for America program.

Get full access

See the source behind every fact, the full slippage tracker and complete change history, plus CSV export, unlimited alerts, and API access with a Pro subscription.

View Pricing

Evidence

  • StatusConfirmed
  • ScheduleConfirmed

See the evidence

Source links, notes and check dates for every verified fact.

Upgrade to Pro

General references

Starting points for this project — not a verification of any figure. See Evidence for what has been checked.