Corrections log
When we got it wrong, we say so
We check our dataset against company filings, press releases and government sources, project by project. When a figure or date we published turns out to be wrong, we fix it and record here what it used to say, what it says now, why, and the source. Nothing is edited quietly.
Corrections
89
Projects fixed
55
Latest
Oct 8, 2026
October 8, 2026 · 11
STMicroelectronics
Catania SiC Substrate CampusStatusUnder ConstructionOperationalSTMicroelectronics' Form 6-K (Jul 30, 2026) states that in the second quarter of 2026 it 'started our manufacturing activities and entered into the ramp-up phase' of the new 200mm silicon carbide manufacturing in Catania. The date shown is the end of that quarter (Jun 27, 2026); ST gives no exact day. The filing refers to the 200mm manufacturing; the separate substrate plant on the campus was not separately confirmed.
Source: sec.govSK Hynix
Cheongju M15X FabStatusUnder ConstructionOperationalCoverage of SK hynix's Q2 2026 earnings call says M15X's cleanroom opened in October 2025, wafer input began in the first quarter of 2026, and SK hynix expects to ramp volume gradually (and to accelerate the schedule further). The date shown is the end of Q1 2026; no exact day was given. The record previously showed Under Construction.
Source: investing.comBAE Systems
Nashua NH Microelectronics CenterInvestment$1.2B$105MThe U.S. CHIPS program's project page lists an expected capital expenditure of $105 million for the Nashua modernization (up to $35.5M of it from a finalized CHIPS award); the record showed $1.24 billion, about 12x too high.
Source: nist.govBAE Systems
Nashua NH Microelectronics CenterPlanned startJan 1, 2026Jan 1, 2028The CHIPS program page says the project is expected to be completed by approximately 2028; the record showed 2026.
Source: nist.govApplied Materials
Silicon Valley EPIC Centerlocation_citySanta ClaraSunnyvaleAn earlier correction in this log moved this entry from Austin to Santa Clara. The EPIC Center is actually on Applied Materials' existing campus in Sunnyvale, CA (next to its Maydan Technology Center on Arques Avenue), so the city and map pin are corrected again. The map pin is city-level, not the exact site.
Source: rmw.comSkyWater Technology
Bloomington MN Fab ExpansionPlanned startJan 1, 2026TBDNo completion date has been published for SkyWater's Bloomington modernization; the CHIPS award is still described as a proposed preliminary term sheet. The record's Jan 2026 date had no source.
Source: nist.gov- Planned startJan 1, 2025TBD
X-Fab's May 2023 announcement of the $200 million Lubbock expansion gave no completion date, and no 2026 confirmation that the expanded capacity is running was found. The record's Jan 2025 date had no source and has already passed.
Source: kcbd.com STMicroelectronics
Crolles Fab Expansion (JV w/ GlobalFoundries)Planned startJan 1, 2026TBDThe joint ST/GlobalFoundries Crolles fab has been reported as stalled since early 2025, and a Jan 2026 report says GlobalFoundries has not met its commitments; no revival or new production date was found. The original full-capacity-in-2026 target is no longer realistic, so the date is removed. ST's own separate Crolles expansion decision (expected by end-2026) is a different project.
Source: digitimes.com- Planned startJan 1, 2025TBD
The record's Jan 2025 date has already passed and no company or government source for any production date was found (public site-level disclosure for this project is limited), so the date now shows TBD rather than a stale, unsourced one.
Powerchip Semiconductor Manufacturing Corp
Kaohsiung FabPlanned startJan 1, 2025TBDThe record's Jan 2025 date has already passed and no company or government source for any production date was found (public site-level disclosure for this project is limited), so the date now shows TBD rather than a stale, unsourced one.
- Planned startJan 1, 2025TBD
The record's Jan 2025 date has already passed and no company or government source for any production date was found (public site-level disclosure for this project is limited), so the date now shows TBD rather than a stale, unsourced one.
September 28, 2026 · 38
- Investment$3.0B$1.1B
Multiple sources consistently describe the Dresden fab as a roughly EUR 1 billion investment, Bosch's largest single investment in its 130+ year history at the time (about $1.1B at the prevailing exchange rate). Further incremental investment was announced in 2022-2023, but no single total near the record's $3.0B was found.
Source: techpowerup.com - Investment$2.0B$450M
Coverage of onsemi's Aug 2022 expansion celebration describes a $150 million investment already made, with plans for a further $300 million through 2023 (about $450M total); the record showed $2.0B, off by roughly 4-5x.
Source: businesswire.com - StatusUnder ConstructionOperational
onsemi's own release (Aug 2022) describes the expanded facility as already increasing SiC boule production capacity by 5x year-over-year; the record showed Under Construction with a 2026 target, which does not match.
Source: businesswire.com GlobalFoundries
Burlington VT ExpansionInvestment$4.0B$900MVermont's federal CHIPS funding ($125M) supports a $900 million 'Fab 9' expansion at GlobalFoundries' Essex Junction (Burlington area) site, per Vermont media coverage (Feb 2024). The record's $4.0B figure appears to have used a combined New York + Vermont total instead of the Vermont-specific figure.
Source: wcax.com- Investment$275M$315M
Press coverage of the CHIPS award (up to $32M in federal funding) describes Corning's own investment in the Canton expansion as $315 million; the record showed $275M.
Source: northcountrynow.com - Investment$300M$200M
KLA's investment grew in stages: $70M (announced Oct 2018), raised to $150M (2019), and reported at a total of $200M by the Nov 5, 2021 ribbon-cutting. The record showed $300M, which we could not source; $200M is the last figure we could confirm, and the total may have grown further since 2021 without a source we found.
Source: michigan.gov - Actual startJan 1, 2022Nov 5, 2021
Michigan's governor's office held a ribbon-cutting for the completed Ann Arbor facility on Nov 5, 2021; the record showed Jan 1, 2022.
Source: michigan.gov Edwards Vacuum
Chandler AZ Manufacturing FacilityActual startJan 1, 2023Apr 20, 2023The Chandler Connection facility officially opened on Thursday, Apr 20, 2023, per the City of Chandler; the record showed Jan 1, 2023.
Source: chandleraz.govLam Research
Tualatin OR ExpansionStatusOperationalUnder ConstructionLam Research broke ground on a new AI-era R&D lab at its Tualatin campus on Aug 26, 2026, with a Washington County/Tualatin agreement covering up to $1.7B in investment through 2041 and the lab projected to open in 2028. The record showed this as operational since 2023 at $1.0B, which does not match any announcement found.
Source: prnewswire.comLam Research
Tualatin OR ExpansionInvestment$1.0B$1.7BWashington County's Strategic Investment Program agreement covers up to $1.7 billion through 2041; the record showed $1.0B.
Source: washingtoncountyor.govLam Research
Tualatin OR ExpansionPlanned startJan 1, 2023Jan 1, 2028The new Oregon lab is projected to open in 2028, per coverage of the Aug 26, 2026 groundbreaking; the record showed 2023.
Source: prnewswire.com- Actual startJan 1, 2023Nov 5, 2025
Entegris celebrated the grand opening of its Colorado Springs Manufacturing Center of Excellence on Nov 5, 2025; the record showed Jan 1, 2023, which predates even the Dec 2022 announcement of the project.
Source: finance.yahoo.com Microchip Technology
Gresham OR Fab ExpansionInvestment$880M$800MGresham's own multi-year expansion is described as an $800 million initiative (separate from the $880M figure for Microchip's Colorado Springs site, which the record had duplicated here).
Source: merkley.senate.govTexas Instruments
Richardson TX Fab ExpansionInvestment$3.0B$3.1BGovernor Abbott's office announced (Apr 18, 2019) that the new RFAB2 facility represents 'more than $3.1 billion in capital investment'; the record showed $3.0B, a close but imprecise figure.
Source: gov.texas.govTexas Instruments
Richardson TX Fab ExpansionActual startJan 1, 2022Sep 1, 2022TI's own blog post says RFAB2 started initial production in September 2022, 13 years after RFAB1 opened; the record showed Jan 1, 2022.
Source: ti.comNXP Semiconductors
Chandler AZ Fab ExpansionInvestment$2.0B$100MThis was a retrofit of an existing site, not a new fab: NXP invested about $100 million over three years to convert it to a 150mm RF GaN fab. The record showed $2.0 billion, off by roughly 20x.
Source: azcommerce.comNXP Semiconductors
Chandler AZ Fab ExpansionActual startJan 1, 2024Sep 29, 2020NXP opened the GaN fab on Sep 29, 2020; the record showed Jan 1, 2024, which appears to have been confused with an unrelated date.
Source: azcommerce.comNXP Semiconductors
Chandler AZ Fab ExpansionStatusOperationalOperationalNo field value changed here; this entry records context only. Press reports (Aug 2026) say Nokia will acquire NXP's Chandler GaN fab, leasing part of it from early 2027 and completing the purchase in Q1 2029, with NXP closing its own use of the site by 2027. Our status field still shows Operational, which is accurate today, but this project should be revisited as that timeline approaches.
Source: semiconductor-today.comUnited Microelectronics Corp
Tainan Fab 12A P6 Expansionproject_nameTainan Fab 12A P7 ExpansionTainan Fab 12A P6 ExpansionThe record's investment (NT$100B) and 2023 production date match UMC's Fab 12A Phase 6 (P6) expansion, announced Apr 28, 2021. A separate, still-unbuilt Phase 7 (P7) only had its fab shell announced in Jul 2026 with no production date, and does not match this record. Renamed from P7 to P6 to reflect the sourced facts; the two phases were likely confused when the record was created.
Source: streetinsider.com- Actual startJan 1, 2023Jan 24, 2024
Intel's own release states Fab 9 opened on Jan 24, 2024; the record showed Jan 1, 2023.
Source: intc.com SkyWater Technology
Bloomington MN Fab ExpansionInvestment$1.3B$127MThis is a facility modernization, not a new fab: the U.S. Commerce Dept's Dec 2024 preliminary CHIPS Act terms describe a total project cost of about $127 million (up to $16M in CHIPS direct funding plus other financing), improving wafer capacity by 30%. The record showed $1.3 billion, which appears to be off by roughly 10x.
Source: businessfacilities.com- Actual startJul 1, 2022Jun 1, 2021
Press coverage says Bosch's Dresden wafer fab opened in June 2021 (a EUR 1 billion investment, its largest ever at the time), with further incremental investment announced in 2022 and 2023. The record showed Jul 1, 2022. The record's $3.0B investment figure could not be matched to a single Bosch statement this round and is left unverified rather than changed on an uncertain match.
Source: greencarcongress.com Samsung
Taylor TX Fab Phase 2Planned startTBDDec 31, 2030The Elec (Jul 30, 2026) reports Taylor Fab 2 construction is scheduled to begin by the end of 2026, with commercial production currently targeted for 2030. The record previously had no date (TBD) after an earlier, unsupported 2029 figure was removed.
Source: thelec.net- Investment$7.6B$6.9B
Digitimes (Feb 20, 2025) reports SMIC's Beijing fab expansion (second phase) at a total investment of at least CNY 50 billion (about US$6.86 billion); the record showed $7.6B with no identifiable source.
Source: digitimes.com - StatusAnnouncedUnder Construction
TSMC's Arizona page states it broke ground on the third fab (N2/A16) in April 2025; the record still showed Announced.
Source: tsmc.com Vanguard International Semiconductor / NXP
Singapore VSMC JV FabStatusAnnouncedUnder ConstructionNXP's Dec 4, 2024 release describes VSMC 'celebrating breaking ground' on the 300mm fab, so construction has started; the record showed Announced.
Source: nxp.comGlobalFoundries
Malta NY ExpansionPlanned startJan 1, 2027TBDNo GlobalFoundries or government statement giving a production date for the new Malta fab was found. The Feb 2024 announcement says construction was scheduled to begin in 2025 but states no production date; the record's Jan 2027 figure had no source.
Source: governor.ny.govPower Chip Semiconductor Manufacturing Corp (PSMC/SBI)
Miyagi JSMC FabStatusUnder ConstructionDelayedReports say PSMC's board confirmed it is ending its partnership with SBI Holdings on the Miyagi JSMC project, with PSMC declining to assume the project's risk; SBI says it intends to continue by finding a new partner. The record showed Under Construction with no indication of this. Not marked Cancelled because SBI has said it intends to proceed.
Source: dig.watchGlobalFoundries
Singapore Fab 7Actual startJun 1, 2023Sep 12, 2023GlobalFoundries officially opened its $4 billion Singapore expansion fab (Fab 7h) on Sep 12, 2023; the record showed Jun 1, 2023.
Source: gf.com- Investment$3.9B$4.0B
Purdue University's release of the Aug 27, 2026 groundbreaking describes the project as a $4 billion investment; the record showed $3.87B.
Source: purdue.edu Amkor Technology
Peoria AZ Advanced Packaging FacilityInvestment$2.0B$7.0BAmkor's Oct 2025 groundbreaking release headline states the investment was expanded to $7 billion across two phases; the record showed $2.0 billion.
Source: azcommerce.comAmkor Technology
Peoria AZ Advanced Packaging FacilityPlanned startJan 1, 2027Jan 1, 2028Press coverage of the Oct 2025 groundbreaking says construction of the first facility completes mid-2027 with production beginning early 2028; the record showed 2027. Amkor's own release body was not opened to confirm the exact wording.
Source: azcommerce.comMicron
Hiroshima Fab ExpansionPlanned startJan 1, 2027Dec 31, 2028Micron broke ground on the Hiroshima expansion on Jul 4, 2026 (investment reported at about JPY 1.5 trillion, with up to JPY 500 billion of METI subsidy). Trade press reports equipment installation is set for the second half of 2028; the record showed 2027, which predates the groundbreaking itself.
Source: trendforce.comApplied Materials
Silicon Valley EPIC Centerlocation_cityAustinSanta ClaraThe EPIC Center was announced for an Applied Materials campus in Silicon Valley (Santa Clara, CA), not Austin, TX; the record had the wrong city, state and project name. Investment was also updated from $4.0B (the original May 2023 figure) to $5.0B, per Applied's Feb 11, 2026 release.
Source: ir.appliedmaterials.comApplied Materials
Silicon Valley EPIC CenterInvestment$4.0B$5.0BApplied's Feb 11, 2026 release describes the EPIC Center as its 'multibillion-dollar' campus and cites approximately $5 billion; the record showed the original $4.0B figure from the May 2023 announcement.
Source: ir.appliedmaterials.comIntel
Chandler Fab 62Planned startJan 1, 2025TBDThe record's Jan 2025 target has already passed with no Intel confirmation of production start. Press (Tom's Hardware) reports Fab 62 is expected to be ready around 2028, but Intel has not stated a date, so the field now shows TBD.
- Planned startJan 1, 2028TBD
TrendForce (Jul 31, 2026) reports Israel withdrew a $425M grant for Intel and the Kiryat Gat expansion remains uncertain, following an earlier construction halt. Intel has not restated a production date since pausing the project, so the 2028 date is removed.
Source: trendforce.com - Planned startJan 1, 2025Jan 1, 2027
The record's Jan 2025 target has passed. Trade press describes TSMC's AP7 advanced-packaging complex at this Chiayi site as targeting equipment move-in for Phase 1 in 2026 and mass production in 2027; investment for this entry is unchanged and unverified.
Source: trendforce.com
September 23, 2026 · 9
Samsung
Taylor TX Fab Phase 2Planned startJan 1, 2029TBDSamsung said in March 2026 that it has no specific timeline to build a second fab in Taylor; the city council is preparing for possible first steps as early as the end of 2026, depending on market conditions. The 2029 date shown before was not supported by any Samsung statement, so it now shows TBD.
Source: taylorpress.netIntel
Leixlip Fab 34Actual startSep 1, 2023Sep 29, 2023Intel announced on September 29, 2023 that Fab 34 in Ireland began high-volume manufacturing on Intel 4; the record showed September 1, 2023.
Source: intc.comSK Hynix
Cheongju M15X FabPlanned startJan 1, 2025Nov 30, 2025SK hynix's April 24, 2024 announcement says M15X construction would start at the end of April 2024 and be completed in November 2025 for early mass production; the record showed January 2025, which no SK hynix statement supports.
Source: news.skhynix.comTexas Instruments
Sherman SM2Planned startJan 1, 2026TBDTI has announced no production date for this fab. Its Sherman page and its Dec 17, 2025 release (which announced SM1 production) describe SM2 to SM4 only as future fabs to be built and equipped in line with market demand. The date shown before was not supported by any TI statement, so it now shows TBD.
Source: ti.comTexas Instruments
Sherman SM3Planned startJan 1, 2029TBDTI has announced no production date for this fab. Its Sherman page and its Dec 17, 2025 release (which announced SM1 production) describe SM2 to SM4 only as future fabs to be built and equipped in line with market demand. The date shown before was not supported by any TI statement, so it now shows TBD.
Source: ti.comTexas Instruments
Sherman SM4Planned startJan 1, 2030TBDTI has announced no production date for this fab. Its Sherman page and its Dec 17, 2025 release (which announced SM1 production) describe SM2 to SM4 only as future fabs to be built and equipped in line with market demand. The date shown before was not supported by any TI statement, so it now shows TBD.
Source: ti.com- Planned startJan 1, 2027Dec 31, 2027
TSMC's Aug 8, 2023 release says ESMC production is targeted to begin by the end of 2027; the record showed January 2027. ESMC's president said on Sep 14, 2026 that the fab is on schedule and first process equipment goes in during the second half of 2027.
Source: pr.tsmc.com TSMC
Kaohsiung Fab 22Actual startJan 1, 2025Dec 31, 2025TSMC's N2 (2nm) technology page states volume production started in 4Q25 as planned, and Taiwanese press (Focus Taiwan, Dec 30, 2025) reported the start. Trade press places that production at Kaohsiung Fab 22, but TSMC does not name the fab. The record previously showed a January 2025 target that had passed. The date shown is the end of that quarter.
Source: tsmc.comSamsung
Pyeongtaek P4 ExpansionPlanned startJan 1, 2026Dec 31, 2026Seoul Economic Daily (Apr 23, 2026) reports Samsung will bring P4 to full operation within 2026, about six months ahead of the original schedule; P4 is currently running at half capacity, with temporary-use approvals targeted for July and November 2026. The record previously showed January 2026.
Source: en.sedaily.com
September 20, 2026 · 3
Wolfspeed
Siler City NC SiC Materials FacilityStatusUnder ConstructionOperationalWolfspeed's Oct 29, 2025 earnings release says Siler City attained production readiness in late fiscal 2025 (the fiscal year ended June 29, 2025), after which its costs moved out of start-up costs. Status changed from under construction; the date shown is the fiscal year-end.
Source: sec.gov- Planned startJan 1, 2027Dec 31, 2027
TSMC's Feb 6, 2024 release scheduled JASM's second fab to begin operation by the end of 2027; the record showed January 2027. TSMC later delayed the construction start over traffic congestion, and press reports suggest operations could slip to 2029, but TSMC has not restated a new operating date.
Source: pr.tsmc.com Intel
Chandler Fab 52Actual startJun 1, 2023Oct 9, 2025Intel announced on October 9, 2025 that Arizona Fab 52 is fully operational and set to reach high-volume production on Intel 18A later that year. The record previously showed June 2023, which was not supported by any Intel statement.
Source: intc.com
September 19, 2026 · 28
Texas Instruments
Sherman SM1Investment$7.5B$10.0BTI's Sherman page states a potential $40 billion investment for up to four connected fabs (SM1 to SM4); the record split $30 billion across four entries. Now split evenly.
Source: ti.comTexas Instruments
Sherman SM2Investment$7.5B$10.0BTI's Sherman page states a potential $40 billion investment for up to four connected fabs (SM1 to SM4); the record split $30 billion across four entries. Now split evenly; the entries use TI's SM1-SM4 fab names.
Source: ti.comTexas Instruments
Sherman SM3Investment$7.5B$10.0BTI's Sherman page states a potential $40 billion investment for up to four connected fabs (SM1 to SM4); the record split $30 billion across four entries. Now split evenly; the entries use TI's SM1-SM4 fab names.
Source: ti.comTexas Instruments
Sherman SM4Investment$7.5B$10.0BTI's Sherman page states a potential $40 billion investment for up to four connected fabs (SM1 to SM4); the record split $30 billion across four entries. Now split evenly; the entries use TI's SM1-SM4 fab names.
Source: ti.com- Investment$8.6B$7.0B
TSMC's Nov 9, 2021 release states JASM's initial capital expenditure at approximately US$7 billion; the record showed $8.6 billion.
Source: pr.tsmc.com STMicroelectronics
Crolles Fab Expansion (JV w/ GlobalFoundries)StatusUnder ConstructionDelayedEuropean trade press reported on January 21, 2025 that STMicroelectronics and GlobalFoundries had shelved their planned EUR 7.5 billion joint Crolles fab. Neither company has confirmed the reports, so this is labeled Reported and shown as Delayed rather than Cancelled.
Source: eenewseurope.comMicron
Hiroshima Fab ExpansionInvestment$6.7B$10.0BReports of the September 2025 announcement say Micron plans to invest approximately JPY 1.5 trillion (about $10 billion) in its Hiroshima site, alongside up to JPY 536 billion of Japanese government subsidy. The record showed $6.7 billion.
Source: trendforce.comSK Hynix
Cheongju M15X FabInvestment$5.3B$14.3BSK hynix stated on April 24, 2024 that M15X construction is about 5.3 trillion won and total investment will be more than 20 trillion won long term (about $14 billion). The record showed $5.3 billion, which appears to have read won as dollars.
Source: news.skhynix.comInfineon Technologies
Dresden Smart Power FabStatusUnder ConstructionOperationalInfineon opened its Smart Power Fab in Dresden on July 2, 2026, describing it as a EUR 5 billion investment.
Source: prnewswire.comSamsung
Pyeongtaek P4 ExpansionInvestment$30.0B$36.0BReporting in April 2026 says Samsung will bring Pyeongtaek P4 into full operation this year, having invested 50 trillion won (about $36 billion). The record showed $30 billion.
Source: en.sedaily.comSK Hynix
Yongin Semiconductor ClusterInvestment$90.0B$425.0BSK hynix announced on June 29, 2026 a long-term plan allocating 600 trillion won to the Yongin semiconductor cluster (about $425 billion at the recent rate of roughly 1,410 won per dollar). The record showed $90 billion, from the company's earlier 120 trillion won plan.
Source: thelec.netIntel
Chandler Fab 52Investment$17.5B$10.0BIntel's Sept 24, 2021 release states a $20 billion expansion for the two new Arizona fabs combined; the record had $17.5 billion for each, which double-counted. Now split evenly.
Source: intc.comIntel
Chandler Fab 62Investment$17.5B$10.0BIntel's Sept 24, 2021 release states a $20 billion expansion for the two new Arizona fabs combined; the record had $17.5 billion for each, which double-counted. Now split evenly.
Source: intc.comTSMC
Kaohsiung Fab 22Investment$13.0B$45.2BTSMC's co-COO stated on March 31, 2025 that TSMC is investing more than NT$1.5 trillion (about US$45 billion) in its Kaohsiung complex; the record showed $13 billion.
Source: focustaiwan.twIntel
Leixlip Fab 34Investment$32.0B$18.4BIntel stated on June 4, 2024 that it had invested $18.4 billion in Fab 34; the record showed $32.0 billion, which no Intel source supports for this fab.
Source: intc.comSamsung
Taylor TX R&D CenterInvestment$5.0BNot shownNIST states Samsung's total expected spend is over $37 billion across its Taylor and Austin sites, including two logic fabs and an R&D fab. The R&D center is part of that total, so its separate $5 billion was removed to avoid double-counting.
Source: nist.gov- Investment$20.0B$13.9B
TSMC states overall investment in JASM will exceed US$20 billion for both Kumamoto fabs combined, so a separate $20 billion for the second fab double-counted. Reports put the second fab at about $13.9 billion.
Source: pr.tsmc.com SK Hynix
Yongin Semiconductor ClusterPlanned startJan 1, 2027Feb 1, 2027SK hynix stated on February 25, 2026 that the opening of the first cleanroom at its first Yongin fab is moved up from May to February 2027. The record now tracks that milestone; it previously showed January 2027.
Source: news.skhynix.comKioxia
Kitakami Fab 2 ExpansionStatusUnder ConstructionOperationalKioxia and Sandisk announced on September 29, 2025 the start of operation at Fab2 (K2) at the Kitakami Plant. Output ramps in stages, with meaningful output expected in the first half of 2026.
Source: kioxia.com- Investment$65.0BNot shown
TSMC describes its Arizona investment as one cumulative program (total $265 billion), not per-phase amounts. Phase-level figures were removed to avoid double-counting; the program total is shown on the Phase 3 onward entry.
Source: tsmc.com - Investment$65.0BNot shown
TSMC describes its Arizona investment as one cumulative program (total $265 billion), not per-phase amounts. Phase-level figures were removed to avoid double-counting; the program total is shown on the Phase 3 onward entry.
Source: tsmc.com - Investment$165.0B$265.0B
TSMC's Arizona page states a total planned investment of $265 billion (expanded from $165 billion in March 2025 and $12 billion originally). This entry now carries the whole-program figure, which includes Phases 1 and 2.
Source: tsmc.com GlobalFoundries
Malta NY ExpansionInvestment$12.0B$11.6BThe New York governor's announcement (Feb 19, 2024) states GlobalFoundries will invest more than $11.6 billion over 10 years at Fab 8; the record showed $12.0 billion.
Source: esd.ny.govSamsung
Taylor TX Fab Phase 1Planned startJan 1, 2026Dec 31, 2026Samsung stated on April 24, 2026 that the Taylor plant will be operational by the end of 2026; the record previously showed January 2026.
Source: taylorpress.netIntel
Ohio One Fab 2Planned startJan 1, 2031Jan 1, 2032Intel's Feb 28, 2025 timeline update says Mod 2 construction completes in 2031 with operations beginning in 2032; the record previously showed 2031.
Source: intel.com- Actual startApr 1, 2024Oct 1, 2024
TSMC states high-volume production of N4 at its first Arizona fab started in Q4 2024; the record previously showed April 2024.
Source: tsmc.com - Planned startJan 1, 2027Jul 1, 2027
TSMC states volume production of N3 at its second Arizona fab is targeted for the second half of 2027; the record previously showed January 2027.
Source: tsmc.com Texas Instruments
Sherman SM1Actual startJan 1, 2025Dec 17, 2025Texas Instruments announced on December 17, 2025 that its first Sherman, Texas fab (SM1) began production; the record previously showed January 2025 and used an incorrect fab name.
Source: ti.com
Found something we should fix? Email hello@getfabpulse.com with a source. See also our methodology.