Rogue Valley Microdevices

Medford OR Fab Expansion

Medford, OR, USA

Operational
StatusReportedScheduleUnverifiedInvestmentUnverifiedWhat do these mean?
LinkedInX

Investment

$40M

CHIPS Act Funding

$6M

Technology Node

MEMS/specialty

Jobs Created

100

Project Type

Foundry

Planned HVM Start

Jan 1, 2024

Actual HVM Start

Jan 1, 2024

Last Updated

Sep 3, 2026

Schedule slippage

No verified schedule baseline yet for this project. We add baselines only once we can cite an official earlier target — nothing is estimated.

Timeline

No milestones recorded for this project yet.

History of Changes

No changes detected yet for this project.

CHIPS Act Funding

$6M

Direct funding award disclosed by the U.S. Department of Commerce's CHIPS for America program.

Get full access

See the source behind every fact, the full slippage tracker and complete change history, plus CSV export, unlimited alerts, and API access with a Pro subscription.

View Pricing

Evidence

  • StatusReported

See the evidence

Source links, notes and check dates for every verified fact.

Upgrade to Pro

General references

Starting points for this project — not a verification of any figure. See Evidence for what has been checked.