← All projects

BAE Systems

Nashua NH Microelectronics Center

Nashua, NH, USA

Under Construction
StatusReportedScheduleConfirmedInvestmentConfirmedWhat do these mean?
LinkedInX

Investment

$105M

CHIPS Act Funding

$35M

Technology Node

RF/mixed-signal

Jobs Created

400

Project Type

Foundry

Planned HVM Start

Jan 1, 2028

Actual HVM Start

Not yet in production

Last Updated

Oct 8, 2026

Schedule slippage

No verified schedule baseline yet for this project. We add baselines only once we can cite an official earlier target — nothing is estimated.

Timeline

No milestones recorded for this project yet.

History of Changes

Data correction: The U.S. CHIPS program's project page lists an expected capital expenditure of $105 million for the Nashua modernization (up to $35.5M of it from a finalized CHIPS award); the record showed $1.24 billion, about 12x too high.

Oct 8, 2026 · investment_usd changed from "1240000000" to "105000000"

1 earlier change in the full history

Every change to this project, each with its source.

Upgrade to Pro

CHIPS Act Funding

$35M

Direct funding award disclosed by the U.S. Department of Commerce's CHIPS for America program.

Get full access

See the source behind every fact, the full slippage tracker and complete change history, plus CSV export, unlimited alerts, and API access with a Pro subscription.

View Pricing

Evidence

  • InvestmentConfirmed
  • ScheduleConfirmed
  • StatusReported

See the evidence

Source links, notes and check dates for every verified fact.

Upgrade to Pro

General references

Starting points for this project — not a verification of any figure. See Evidence for what has been checked.